First PIM - July 2006
Second PIM - February 2007
Third PIM - November 2007
Fourth PIM - March 2008
Design Completion - On-hold *
Row Acquisition - On-hold *
Advertise/Bidding - On-hold *
Construction Begin - On-hold *
Construction Cost - $8.0 Million *
|
|
|
|
|
|
|
|
|
|
|
|
|
|
* July 2011 - Obtaining permits for preferred slope stability alternative. Construction funds currently scheduled for 2015. |
|
|
|
|
|
| |